Hillcrest Drive is Open

Share on RSS

 

Tom Davis
The wait is over for some Bartlesville motorists as Hillcrest Drive is open follwing a 3-week closure to facilitate the Hillcrest Drive Rehabilitation Project.
 
The city of Bartlesville posted the the reopening just after 11a.m. on their Facebook page on Monday. 
 
The $2.2 million project, approved by voters in the 2013 Half-cent Capital Improvement Project election, involved reconstructing Hillcrest Drive from the Caney River to just north of 20th Street. 
 
The new alignment transitions to the existing roadway just north of the Caney River on the south end of the project and just north of 20th Street on the north end of the project.
 
The new roadway consists of two 12-foot-wide drive lanes with six-foot-wide asphalt shoulders. Turn lanes have been constructed at Shawnee Avenue and 20th Street. A pedestrian path will also be constructed in the area.